Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Delay (No. of months) | Current Physical Status | ||
---|---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | ||||
Project Milestone-I | 146 | 20 | 05.04.2023 | 21.01 | 30.06.2023 | 2 months | 21.01 % |
Project Milestone-II | 256 | 35 | 24.07.2023 | 35.40 | 21.10.2023 | 2 months | 68.29 % |
Project Milestone-III | 548 | 75 | 11.05.2024 | 75.55 | 30.06.2024 | 2 months | 82.69 % |
Schedule Completion | 730 | 100 | 09.11.2024 | 85.39% |