Project Milestone Status

Project Milestones Status

Project Milestone Description (Days from Appointed Date) Planned Actual Delay (No. of months) Current Physical Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 146 20 05.04.2023 21.01 30.06.2023 2 months 21.01 %
Project Milestone-II 256 35 24.07.2023 35.40 21.10.2023 2 months 68.29 %
Project Milestone-III 548 75 11.05.2024 75.55 30.06.2024 2 months 82.69 %
Schedule Completion 730 100 09.11.2024       85.39%