Physical Progress

Physical Progress

Component %Weightage as per Schedule-G Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads)
61.95%
0.59%
59.25%
Major Bridge Works & ROB/ RUB
8.23%
0.21%
6.87%
Structures (elevated sections, reinforced earth)
4.59%
4.25%
Electrical and Public Health Utilities
2.40%
1.30%
Other Works
22.83%
0.43%
13.72%
Total
100.00%
1.23%
85.39%