Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 61.95% |
0.002% |
61.61% |
Major Bridge Works & ROB/ RUB | 8.23% |
0.167% |
7.82% |
Structures (elevated sections, reinforced earth) | 4.59% |
0.035 |
4.55% |
Electrical and Public Health Utilities | 2.40% |
1.75% |
|
Other Works | 22.83% |
0.35% |
19.75% |
Total |
100.00% |
0.56% |
95.49% |