Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 61.95% |
0.20% |
57.35% |
Major Bridge Works & ROB/ RUB | 8.23% |
0.36% |
6.53% |
Structures (elevated sections, reinforced earth) | 4.59% |
4.57% |
|
Electrical and Public Health Utilities | 2.40% |
1.22% |
|
Other Works | 22.83% |
0.21% |
13.02% |
Total |
100.00% |
0.77% |
82.69% |